Kealakehe Wastewater Treatment Plant R1 Project

PROJECT TIMELINE


The request for proposals (RFP) for the project was posted on the County’s Public Purchase website on August 29, 2025. After the Notice to Proceed is issued, this webpage will be updated with project information.

 

 

PROJECT MILESTONES


🟢

RFP

ISSUED

8/29/2025

🚧

CONSTRUCTION

START

3/1/2026

REUSE FEASIBILITY 

STUDY

10/3/2026

🎉

CONSTRUCTION

FINISHED

6/30/2029

 

 

FAQs 


What is the status of the project?

  • August 29, 2025: Request for Proposal (RFP) was issued
  • March 1, 2026: Begin Construction

What is a Request for Proposal?

A Request for Proposal (RFP) is a document the department puts out to ask companies to submit detailed plans and prices for how they would do a project or provide a service.

What is the status of the R-1 Reuse Feasibility Study?

The study will be complete by October 3, 2026. The County will have 6 months from the completion of the study to decide whether to construct/operate the R-1 Reuse Project.

  

 


 